In partnership with Tsakane DJC Mizana is installing Data loggers on the 6E/7E PRASA locomotives, with the view of increasing reliability and availability of the said locos, the project will cover at least 64 Locomotives.
Replacement of Motor Alternators and Motor Generators in 10M5, 10M4 and 5M Metrorail Motor Coaches with a Static Inverter
:: Project started in September 2009 and was completed in March 2010
:: The Scope of work involved installation, commissioning and fault finding
Installation of an onsite GSM based Data logging system on 10M5, 10M4 and 5M Metrorail Motor Coaches September 2009 – March 2010
:: Building and Testing of Electrical Panels +131, +136, PA Box, Auxiliary HT Panel, MALT Panels, and Coach Controller panels for 10M Hybrid Coaches February 2012 – on going
Installation of HVAC units in the Shosholoza Fleet in partnership with Vossloh Kiep